New Blower Building Layout
Augercast Piles for New Blower Building Foundation
Augercast Piles for New Blower Building Foundation
Precast Wall Panels for New Blower Building Construction
Structural Steel Pipe Supports for New Compressed Air Duct System
New Compressed Air Duct System
New Compressed Air Duct System
New Compressed Air Duct System
New Compressed Air Duct System
Structural Steel Pipe Supports for New Compressed Air Duct System
Structural Steel Pipe Supports for New Compressed Air Duct System
Demolition Work in Existing Aeration Basin
Demolition Work in Existing Aeration Basin
Prep Work for Installation of New Aeration Grids
Piping for New Aeration Grids
New Parkson Aeration Installation
Start-up and Testing of New Aeration System
Start-up and Testing of New Aeration System
Augercast Piles for Ductbank Construction
Cast in Place Electrical Manhole
Formwork for New Ductbank
Formwork for New Substation Foundation Pad
New Electrical Substation
New Electrical Substation